Q1
Which document defines how a project is executed, monitored and controlled, and closed?

A. Strategic plan
B. Project charter
C. Project management plan
D. Service level agreement

Answer: C

Q2
Which changes occur in risk and uncertainty as well as the cost of changes as the life cycle of a typical project progresses?

A. Risk and uncertainty increase; the cost of changes increases.
B. Risk and uncertainty increase; the cost of changes decreases,
C. Risk and uncertainty decrease; the cost of changes increases.
D. Risk and uncertainty decrease; the cost of changes decreases.

Answer: C

Q3
Which tool or technique is used in the Plan Scope Management process?

A. Document analysis
B. Observations
C. Product analysis
D. Expert judgment

Answer: D

Q4
Which tool or technique is an examination of industry and specific vendor capabilities?

A. Independent estimates
B. Market research
C. Analytical techniques
D. Bidder conferences

Answer: B

Q5
An input used in developing the communications management plan is:

A. Communication models.
B. Enterprise environmental factors.
C. Organizational communications,
D. Organizational cultures and styles.

Answer: B

Prüfungsvorbereitung Studienmaterial PMI-001 deutsch Project Management Professional v5 www.it-pruefungen.ch

Q6
Regression analysis, failure mode and effect analysis (FMEA), fault tree analysis (FTA), and trend analysis are examples of which tool or technique?

A. Expert judgment
B. Forecasting methods
C. Earned value management
D. Analytical techniques

Answer: D

Q7
The Perform Quality Assurance process occurs in which Process Group?

A. Executing
B. Monitoring and Controlling
C. Initiating
D. Planning

Answer: A

Q8
Enterprise environmental factors are an input to which process?

A. Control Scope
B. Define Scope
C. Plan Scope Management
D. Collect Requirements

Answer: C

Q9
Which process develops options and actions to enhance opportunities and reduce threats to project objectives?

A. Identify Risks
B. Control Risks
C. Plan Risk Management
D. Plan Risk Responses

Answer: D

IT-Prüfungen PMI-001 Project Management Professional v5 www.it-pruefungen.ch

Q10
The process of establishing the policies, procedures, and documentation for planning, developing,managing, executing, and controlling the project schedule is known as:

A. Plan Schedule Management.
B. Develop Project Charter.
C. Develop Schedule.
D. Plan Scope Management.

Answer: A

Q11
Which input to the Manage Stakeholder Engagement process is used to document changes that occur during the project?

A. Issue log
B. Change log
C. Expert judgment
D. Change requests

Answer: B