Q1
Which document defines how a project is executed, monitored and controlled, and closed?

A. Strategic plan
B. Project charter
C. Project management plan
D. Service level agreement

Answer: C

Q2
Which changes occur in risk and uncertainty as well as the cost of changes as the life cycle of a typical project progresses?

A. Risk and uncertainty increase; the cost of changes increases.
B. Risk and uncertainty increase; the cost of changes decreases,
C. Risk and uncertainty decrease; the cost of changes increases.
D. Risk and uncertainty decrease; the cost of changes decreases.

Answer: C

Q3
Which tool or technique is used in the Plan Scope Management process?

A. Document analysis
B. Observations
C. Product analysis
D. Expert judgment

Answer: D

Q4
Which tool or technique is an examination of industry and specific vendor capabilities?

A. Independent estimates
B. Market research
C. Analytical techniques
D. Bidder conferences

Answer: B

Q5
An input used in developing the communications management plan is:

A. Communication models.
B. Enterprise environmental factors.
C. Organizational communications,
D. Organizational cultures and styles.

Answer: B

Prüfungsvorbereitung Studienmaterial PMI-001 deutsch Project Management Professional v5 www.it-pruefungen.ch

Q6
Regression analysis, failure mode and effect analysis (FMEA), fault tree analysis (FTA), and trend analysis are examples of which tool or technique?

A. Expert judgment
B. Forecasting methods
C. Earned value management
D. Analytical techniques

Answer: D

Q7
The Perform Quality Assurance process occurs in which Process Group?

A. Executing
B. Monitoring and Controlling
C. Initiating
D. Planning

Answer: A

Q8
Enterprise environmental factors are an input to which process?

A. Control Scope
B. Define Scope
C. Plan Scope Management
D. Collect Requirements

Answer: C

Q9
Which process develops options and actions to enhance opportunities and reduce threats to project objectives?

A. Identify Risks
B. Control Risks
C. Plan Risk Management
D. Plan Risk Responses

Answer: D

IT-Prüfungen PMI-001 Project Management Professional v5 www.it-pruefungen.ch

Q10
The process of establishing the policies, procedures, and documentation for planning, developing,managing, executing, and controlling the project schedule is known as:

A. Plan Schedule Management.
B. Develop Project Charter.
C. Develop Schedule.
D. Plan Scope Management.

Answer: A

Q11
Which input to the Manage Stakeholder Engagement process is used to document changes that occur during the project?

A. Issue log
B. Change log
C. Expert judgment
D. Change requests

Answer: B

Prüfungsvorbereitung übungstest PgMP Fragenkatalog

Prüfungsvorbereitung übungstest PgMP Fragenkatalog Program Management Professional (PgMP) www.it-pruefungen.ch

QUESTION NO: 1

Your program has 121 stakeholders that you’ll need to communicate with. Your communications management plan defines how the communication should happen, what should be communicated, and the expected modality of the communications. You’ll also need which one of the following as an input to the information distribution process in your program?

A. Change requests
B. Earned value management results
C. Stakeholder analysis plan
D. Performance reports

Answer: C

QUESTION NO: 2

What is the formula to determine earned value (EV) for a program?

A. Percent complete times percent remaining in the program
B. Percent completes time the program cost estimate
C. Percent complete times the program budget at completion
D. Percent complete times the program cost of labor and materials

Answer: C

QUESTION NO: 3

Olive is the program manager for her organization. She has created a request for proposal for a large portion of her program. In this work to be procured she has set several requirements for the vendors to participate. The chief among these requirements is a vendor must have at least four licensed electricians in his team. This requirement for four licensed electricians is an example of which one of the following terms?

A. Screening system
B. Scoring model
C. Vendor analysis requirements
D. Evaluation criteria

Answer: A

QUESTION NO: 4

You are the program manager for your organization. Management has asked you to create a document that will capture the stakeholders concerns, perceived threats, and specific objectives about the program and its projects. What document is management asking you to create in this instance?

A. Requirements document
B. Project charter
C. Business case
D. Scope statement

Answer: D

IT-Prüfungen PgMP Program Management Professional (PgMP) www.it-pruefungen.ch

QUESTION NO: 5

You are the program manager of the NHQ Program. You are working with your program team to ensure that the work in the program is done accurately and according to scope. You are also reviewing the team inspection process that will need to be done to ensure that the work is being done according to the scope. If the work is found to be defective it will need to be corrected before the program customers can inspect the work. What process are you completing to ensure that the work is done accordingly to scope?

A. Quality control
B. Scope verification
C. Quality assurance
D. Planning

Answer: C

QUESTION NO: 6

Your company and a competing company have created a teaming agreement for an opportunity. Through this team agreement you and your competitor can complete a major program for a client. This is, technically, a risk response for both organizations. What type of risk response are you dealing with in this instance?

A. Teaming
B. Exploiting
C. Accepting
D. Sharing

Answer: D

PgMP Prüfungsfragen Program Management Professional (PgMP) www.it-pruefungen.ch

QUESTION NO: 7

A project manager in your program has estimated the cost of a program to be $145,000. As the project manager’s project comes close to completion, the project manager realizes that he has still $27,876 left in his project budget. He decides to add some additional features to the project’s deliverables in an effort to use the remaining budget. These additions will add value to the project and the project customer is likely to enjoy these new features. This is an example of what term?

A. Gold plating
B. Errors and omissions
C. Expert judgment by the project manager
D. Value added change

Answer: A

Prüfungsvorbereitung Prüfungsfragen PMI-SP übungstest

Prüfungsvorbereitung Prüfungsfragen PMI-SP übungstest PMI Scheduling Professional (ICND2 v3.0) www.it-pruefungen.ch

Q1
CORRECT TEXT

Fill in the blank with the appropriate word. When activities are logically linked, they become the .
__________

Answer: Schedule.

Q2
Once the project’s WBS has been created what process may happen next?

A. Estimate activity resources
B. Define activities
C. Estimate activity durations
D. Sequence activities

Answer: B

Explanation:
The define activities process is the process that may begin once the project’s WBS has been completed and approved. It is possible, in some projects, to complete the WBS and the activity list at the same time.
Answer option D is incorrect. Sequencing the activities cannot happen until the activity list has been created.
Answer option A is incorrect. Estimating activity resources is dependent on the activity list, so this choice is not valid.
Answer option C is incorrect. Estimate activity durations are dependent on the activity list, so this choice is not valid.

Q3
Which of the following scheduling techniques identifies the successor activities and the predecessor activities to assist the project manager in sequencing the project work?

A. Precedence Diagramming Method
B. Schedule network template
C. Dependency determination
D. Activity on the Node

Answer: A

Explanation:
The Precedence Diagramming Method uses both predecessors and successors as nodes in the project network diagram. The PDM approach is the most common network diagram approach used.
Answer option C is incorrect. Dependency determination identifies the order of the project work. Answer option B is incorrect. The schedule network template is a tool that uses a previous project network diagram as a base for the current project network diagram. Answer option D is incorrect. Activity on the node places activities on circles within a network diagram. It is an example of the precedence diagramming method.

Q4
You are the project manager of the NHGQ project for your company. You must create and distribute performance reports every week to your key project stakeholders. What communication technique do you normally use to distribute reports?

A. Push technique
B. Many-to-many
C. One-to-one
D. Pull technique

Answer: A

Studienmaterial PMI-SP deutsch PMI Scheduling Professional www.it-pruefungen.ch

Q5
Your project team is executing the project plan and things are going well. Your team has reached its first milestone and is now in the second phase of the project. The project stakeholders have requested that you find a method to reduce the duration of the project. They will reward you and your project team with a 25 percent bonus of the project costs if you can finish the project thirty days earlier than what was already planned. The stakeholders, however, will not approve any additional labor costs as part of the agreement. Which approach could you use to shorten the duration of the project?

A. Perform resource leveling for the project.
B. Crash the project schedule.
C. Fast track the project.
D. Remove things from the project scope.

Answer: C

Explanation:
Fast tracking is a technique for compressing project schedule. In fast tracking, phases are overlapped that would normally be done in sequence. It is shortening the project schedule without reducing the project scope. It does not add any additional labor but it can introduce project risks. Answer option D is incorrect. Removing things from the project scope can reduce the project duration, but it will not satisfy the requirements the stakeholders have identified. Answer option A is incorrect. Resource leveling can actually increase the project duration. Answer option B is incorrect. Crashing can reduce the project duration but it increases the labor expense, something the stakeholders won’t approve.

Q6
The Define Activities process is the first process in the project time management knowledge are a. The Define Activities process creates just three outputs as a result of decomposition, rolling wave planning, templates, and expert judgment. Which one of the following is not an output of the Define Activities process?

A. Activity list
B. Milestone list
C. Activity attributes
D. Project document updates

Answer: D

IT-Prüfungen PMI-SP PMI Scheduling Professional www.it-pruefungen.ch

Q7
You are the project manager of the GHT Project. Ben, one of your project team members, does not understand the idea of a milestone. Which of the following best describes what a milestone is?

A. A significant point in the project
B. A goal of reaching a significant delivery of project benefits by an identified date
C. An imposed date for the project to reach a given point
D. The completion of a project activity that is crucial to project completion

Answer: A

PMI-200 Prüfungsvorbereitung

PMI-200 Prüfungsvorbereitung deutsch PMI-Agile Certified Practitioner (PMI-ACP) Exam www.it-pruefungen.ch

QUESTION 1
Retrospectives provide an opportunity for the team to:

A. Reflect at the end of every iteration and identify improvements that will increase the quality of the product.
B. Participate in a mandatory meeting to share status updates across the team and to ensure that everyone is on track.
C. Understand from the management if the project is achieving the Scope, Quality, Cost, and Schedule goals.
D. Set goals at the beginning of the iteration and identify requirements that can be delivered in that iteration.

Answer: A

QUESTION 2
When interacting with team members, the Agile project manager should:

A. Ask team members to do things by phrasing the statement as a request rather than as a demand.
B. Ignore team member input and emotions when important decisions have to be made.
C. Proceed cautiously when requesting team members to do something likely to make them unhappy.
D. Disagree with the team based on the merit of the issue without considering how the team is feeling.

Answer: A

IT-Prüfungen PMI-200 PMI-Agile Certified Practitioner (PMI-ACP) Exam https://www.it-pruefungen.de/PMI-200.htm

QUESTION 3
An organization adopts Agile practices and implements an incremental delivery strategy. If implemented correctly, the company should recognize improved:

A. procurement processes by requiring vendors to ship materials as needed.
B. project cost management by making incremental payments on contracts.
C. customer satisfaction by specifying project shipping dates in the contract.
D. project Return on Investment (ROI) by releasing individual features to market.

Answer: D

QUESTION 4
Based on the following figure, during Iteration 5, there was an increase in story point value (shown on the graph); however, the team completed all of the work it promised to deliver in the iteration and existing estimates were not changed. From this information, one can infer that:

A. Work was removed from the Product Backlog.
B. Work was added to the Product Backlog.
C. The team’s velocity increased.
D. The team’s velocity decreased.

Answer: B

PMI-200 Prüfungsfragen PMI-Agile Certified Practitioner (PMI-ACP) Exam www.it-pruefungen.ch

QUESTION 5
What is used to provide a simple medium for gathering basic information about stories, recording high-level requirements, developing work estimates, and defining acceptance tests?

A. Story card
B. Burn down chart
C. Retrospective
D. Storyboard

Answer: A

PMI-100 IT-Prüfung, PMI-100 zertifizierung

PMI-100 IT-Prüfung, PMI-100 zertifizierung Certified Associate in Project Management(CAPM) www.it-pruefungen.ch

Q1
Which of the following does NOT assess the value a project brings to an organization?

A. Benefit cost analysis
B. Net present value
C. Value analysis
D. Needs assessment

Answer: C

Q2
Your management has decided that all orders will be treated as “projects” and that project managers will be used to update orders daily, to resolve issues, and to ensure that the customer formally accepts the product within 30 days of completion. Revenue from the individual orders can vary from US $100 to US $150,000. The project manager will not be required to perform planning or provide documentation other than daily status. How would you define this situation?

A. Because each individual order is a “temporary endeavor,” each order is a project.
B. This is program management since there are multiple projects involved.
C. This is a recurring process.
D. Orders incurring revenue over $100,000 would be considered projects and would involve project management.

Answer: C

PMI-100 Prüfungsfragen, PMI-100 Examensfragen Certified Associate in Project Management(CAPM) (ICND2 v3.0)  https://www.it-pruefungen.de/PMI-100.htm

Q3
A project manager in a predominantly hierarchical organization has been assigned a major project with aggressive timelines. The BEST approach for developing an initial project charter in this environment is to:

A. Create a project charter using brainstorming sessions with potential team members and -
stakeholders.
B. Create and present a draft project charter to potential team members and stakeholders to solicit their input.
C. Create a project charter jointly with management for distribution to potential team members and stakeholders.
D. Create a project charter with the functional managers and present it to the sponsor for signature.

Answer: C

Q4
All of the following are correct statements about a project manager EXCEPT:

A. He or she is assigned after the project charter is created.
B. He or she may initiate changes to the project.
C. He or she manages changes and factors that create change.
D. He or she is held accountable for project success or failure.

Answer: A

Prüfungsvorbereitung Studienmaterial PMI-100 deutsch Certified Associate in Project Management(CAPM) www.it-pruefungen.ch

Q5
A new project manager is having difficulty creating a WBS with the team. To alleviate this situation, the project manager should ask for help from:

A. The sponsor.
B. Other project managers.
C. The project management office.
D. The team.

Answer: C

EX0-104 Prüfungsfragen

EX0-104 Prüfungsfragen, EX0-104 Examensfragen TMap Next Foundation (ICND2 v3.0) www.it-pruefungen.ch

QUESTION NO: 1
See the definition below:
Tests in which the supplying party demonstrates that the product particularly meets the functional and non-functional specifications and the technical design, among other things.
Of which test level is this the definition?
A. acceptance test
B. development test
C. system test

Answer: C

QUESTION NO: 2
In which Map phase activity does the pre-test take place?
A. Defining central starting points
B. Intake of the test object
C. Specifying the test object intake
D. Executing (re)tests

Answer: B

Prüfungsvorbereitung Studienmaterial EX0-104 deutsch TMap Next Foundation  https://www.it-pruefungen.de/EX0-104.htm

QUESTION NO: 3
Which defect has an internal cause that can be solved within the test team?
A. a defect in the test basis
B. a defect in the test specification
C. a defect in the test object

Answer: B

QUESTION NO: 4
Under which circumstance can Exploratory Testing be used effectively?
A. when experienced testers with domain knowledge are available
B. when testing must be as brief as possible on the critical path of the project
C. when critical functionality, failure of which can cause severe damage, must be tested

Answer: A

IT-Prüfungen EX0-104 TMap Next Foundation www.it-pruefungen.ch

QUESTION NO: 5
What is not an advantage of applying a test design technique and recording it in the test specifications?
A. that the tests are reproducible
B. that the test specifications are transferable
C. that coverage of 100% is achieved
D. that it provides a justified elaboration of the test strategy

Answer: C

Prüfungsvorbereitung auf EX0-103

Prüfungsvorbereitung auf EX0-103 Studienmaterialien deutsch ISO/IEC 20000 Foundation www.it-pruefungen.ch

QUESTION NO: 1
Which of the following is Problem Management primarily concerned with?

A. Looking at Security Plans
B. Looking at the cause of Incidents
C. Looking at the Change Plan
D. Looking at the Release Strategy

Answer: B

QUESTION NO: 2
What is the objective of a Management System?

A. To define, agree, record and manage levels of services
B. To ensure that Key Performance Indicators (KPIs) are defined for all IT services
C. To ensure that new services and changes to services will be deliverable and manageable at the agreed cost and services quality
D. To provide the policies and the framework that is needed for the effective management and implementation of all IT services

Answer: D

QUESTION NO: 3
Which of the aspects listed below is included in ISO/IEC 20000?

A. Customer communication
B. Employee motivation
C. Social responsibility
D. Standard products

Answer: A

IT-Prüfungen EX0-103 ISO/IEC 20000 Foundation https://www.it-pruefungen.de/EX0-103.htm

QUESTION NO: 4
Which of the following tasks is assigned to each process manager?

A. Channeling data to Problem Management
B. Ensuring the process is running effectively and efficiently
C. Following up on Incidents
D. Setting up Service Level Agreements with the users

Answer: B

QUESTION NO: 5
Which of the following must be included within the Service Management plan?

A. Configuration Item (CI) type
B. Information security controls
C. Return to normal working
D. Tools as appropriate to support the processes

Answer: D

EX0-103 Prüfungsfragen ISO/IEC 20000 Foundation www.it-pruefungen.ch

QUESTION NO: 6
Which service changes should be documented in change records?

A. All service changes
B. Formal closure of services
C. Staff recruitment
D. User training

Answer: A

EX0-110 Prüfungsfragen

EX0-110 Prüfungsfragen, EX0-110 Examensfragen Foundation Bridge Exam IT Service Management ISO/IEC 20000 (ICND2 v3.0) www.it-pruefungen.ch

QUESTION NO: 1
Which of the following is a benefit of ISO/IEC 20000 certification?

A. It guarantees that all certified IT Service Management processes are at least audited by a registered certification body once a year.
B. It shows that a company manages IT Services according to an independently audited quality standard.
C. It shows that a company takes quality seriously and that each service is independently audited before it is being delivered.
D. It shows that the highest possible quality level has been achieved.

Answer: B

QUESTION NO: 2
What shall the Service Level Agreements (SLAs) with the suppliers be aligned with?

A. the Service Level Plans
B. the Service Management Plans
C. the SLAs with the other parties
D. the SLAs with the customers

Answer: D

QUESTION NO: 3
When improving the IT Service Management system, what needs to be considered to ensure ongoing compliance with the service providerWhen improving the IT Service Management system, what needs to be considered to ensure on-going compliance with the service provider? Corporate objectives / requirements?

A. A competitor process managementsystemA competitor? process management system
B. Any standards defined by the company itself
C. The budget available to the Personnel Department
D. The time to update the process documentation

Answer: B

Prüfungsvorbereitung Studienmaterial EX0-110 deutsch Foundation Bridge Exam IT Service Management ISO/IEC 20000  https://www.it-pruefungen.de/EX0-110.htm

QUESTION NO: 4
What is the definition of quality according to ISO 9000?

A. Quality is when all features of a service which are agreed with the customer are being delivered to the customer.
B. Quality is when the expectations from the customer to a certain service or product are being delivered to the customer.
C. Quality is when the requirements and expectations of all stakeholders involved in the product lifecycle are being fulfilled.
D. Quality is when the agreed service levels of a specific and defined service are met during morethen six subsequent periods.

Answer: A

QUESTION NO: 5
Which of the following actions should be taken to ensure continual improvement of a Service Management System?

A. Analyze and evaluate the existing situation to identify areas for improvement.
B. Analyze customer satisfaction and identify resulting actions.
C. Review the Service Management System at least annually.
D. Start an internal service organization evaluation.

Answer: A

IT-Prüfungen EX0-110 Foundation Bridge Exam IT Service Management ISO/IEC 20000 www.it-pruefungen.ch

QUESTION NO: 6
An objective of capacity management is to ensure that the service provider has, at all times, sufficient capacity to meet the current and future agreed demands of the customer’s business needs. What document is produced to support this objective?

A. Availability plan
B. Business resource plan
C. Capacity plan
D. Service Management plan

Answer: C

EX0-111 IT-Prüfungen, EX0-111 zertifizierung

EX0-111 IT-Prüfungen, EX0-111 zertifizierung Green IT Citizen www.it-pruefungen.ch

QUESTION NO: 1
Your company operates a decentralized purchasing model for computer equipment. Individual departments or groups make their own selections as long as they stay within budget. What is the best way to influence decisions towards a greener workplace when purchasing computer equipment?

A. Arrange a meeting with the IT department to show them a list of green vendors.
B. Establish centralized purchasing so that the company as a whole goes green.
C. Focus on education and persuasion of the individual departments or groups to ensure greener purchasing.

Answer: C

QUESTION NO: 2
What does the Electronic Products Environmental Assessment Tool (EPEAT) do?

A. It aligns company policies to national legislation with regards to environmental waste reduction.
B. It rates IT products based on their compliance with the IEEE 1680 standard.
C. It submits a plan for replacing old computers with more efficient computers.

Answer: B

EX0-111 Prüfungsfragen, EX0-111 Examensfragen Green IT Citizen (ICND2 v3.0)  https://www.it-pruefungen.de/EX0-111.htm

QUESTION NO: 3
What is a main source of power costs for e-mail?

A. Reading e-mail
B. Saving e-mail
C. Sending e-mail

Answer: B

QUESTION NO: 4
You want to buy equipment made from materials that are easy to recycle.Is aluminum easy to recycle?

A. Yes
B. No

Answer: A

QUESTION NO: 5
What are carbon offsets?

A. Certificates that represent the payment for some activity that reduces greenhouse gas
emissions.
B. Natural gases produced by rainforests which work against the formation of carbon dioxide (CO2).
C. Power generating installations based on natural sources of energy, such as solar panels and windmills.

Answer: A

Prüfungsvorbereitung Studienmaterial EX0-111 deutsch Green IT Citizen www.it-pruefungen.ch

QUESTION NO: 6
What is the description of Global climate change?

A. Exhaust fumes from daily traffic are contributing to a decrease in air quality that is slowly deteriorating the number of harvestable foods on Earth.
B. Human activity is contributing to a buildup of greenhouse gases in Earth’s atmosphere that is slowly increasing the average temperature near Earth’s surface.
C. IT industry waste is contributing to a buildup of CO2 in the Earth’s ground that is quickly
increasing the average temperature of Earth’s surface.

Answer: B

EX0-115 IT-Prüfungen, EX0-115 zertifizierung

EX0-115 IT-Prüfungen, EX0-115 zertifizierung IT Service Management Foundation based on ISO/IEC 20000 www.it-pruefungen.ch

QUESTION:1

What is known as a temporary solution that enables the user to continue working?

A. Known Error
B. Request For Change (RFC)
C. Service Request
D. Workaround

Answer: D

QUESTION:2

Through which process does the implementation of new or changed services, including closure of a service, need to be planned and approved?

A. Business Relationship Management
B. Change Management
C. Release Management
D. Service Level Management

Answer: B

EX0-115 Prüfungsfragen, EX0-115 Examensfragen IT Service Management Foundation based on ISO/IEC 20000 (ICND2 v3.0) https://www.it-pruefungen.ch/EX0-115.htm

QUESTION:3

Different types of events are reported to the Service Desk. Which event is an incident?

A. Information about the rollout of a specific application
B. A notification that a new toner cartridge has just been installed in a printer
C. A report that the printer is not working
D. A request for the installation of a new bookkeeping package

Answer: C

QUESTION:4

What has to be included in a well defined process?

A. Expected outcomes
B. Functions
C. Statistical support
D. Timelines

Answer: A

Prüfungsvorbereitung auf EX0-115 Studienmaterialien deutsch IT Service Management Foundation based on ISO/IEC 20000 www.it-pruefungen.ch

QUESTION:5

What would increase the amount of detail in the Configuration Management Database (CMDB)?

A. Increasing the scope of the CMDB
B. Increasing the number of attributes of each Configuration Item (CI) in the CMDB
C. Increasing the number of records in the CMDB
D. Increasing the use of the CMDB

Answer: B